Budget adjustments were proposed for the water treatment plant's new ASR Well No. 3, including a $650,000 supplemental appropriation and a reduced engineering contract with Carollo Engineers.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 3, 2026.
Impact analysis
A $650,000 supplemental appropriation to the water capital fund and a reduced engineering contract of $2,406,684.94.
Water customers who rely on the city's groundwater supply.
No groups negatively affected
Mentions & discussions (3)
General - Nov 3, 2026
Several consent items dealt with water: a trash capture device to keep litter out of stormwater, a drought-relief turf replacement program, new utility-locating equipment, and a grant application to consolidate water service at two apartment complexes.
City Council - Jul 21, 2026
Budget adjustments were proposed for the water treatment plant's new ASR Well No. 3, including a $650,000 supplemental appropriation and a reduced engineering contract with Carollo Engineers.
Mandatory 20% water conservation stage to be implemented in Yuba City
Mandatory 20% water conservation stage to be implemented in Yuba City ABC10
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Yuba City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.